Release Plan

A project plan is required for each major and minor project release. The plan should lay out in broad terms what the goals are for the release. As plans are a valuable means for the community to get involved with your project, the plan should be created at the beginning of the release cycle. By establishing the plan early, you give prospective contributors help in determining how they can most usefully contribute, and adopters can prepare their own development schedule and themes. Plans can change during the release cycle.

A plan can be formal or informal. It’s completely reasonable to set up a project board, or tag issues and call that the plan. What is critical is that the plan be communicated via standard project channels (e.g., the project’s dev-list) in a manner that allows community members to be aware of the project team’s priorities for the and how they can best contribute to the success of the release.

Tip: Release records can be used to capture a project plan. All project leads and committers can use the Create a new release command on their project page to create a new release record.At the start of the release cycle, a plan should minimally include a release number, date, and short description.

All aspects of a plan can change during the release cycle (including the date). If you do change the plan, make sure that the change is communicated via your project’s communication channels.

Producing regular builds is an important part of the release cycle. Builds are an important means of engaging with the community: adopters can help you test your code and test their own so that they can be ready for the eventual release. Project teams should plan to produce at least one milestone build (more are better, depending on the length of your release cycle), and capture the planned date for that milestone in the release record. It is also common practice to generate nightly and weekly integration builds. Project teams must ensure that their project’s downloads page provides the information required for the community to obtain builds.

Pre-release Milestone Builds

Milestone builds and release candidates are not themselves official releases. Per the Eclipse Foundation Development Process, milestone and release candidate builds are pre-releases that are intended to be consumed by a limited audience to solicit, gather, and incorporate feedback from leading edge consumers. A predictable schedule for the delivery of milestone builds is especially valuable when the period of time between formal releases spans multiple months.

Project teams should include at least one milestone build during every release cycle. The timing of milestone and release candidate builds should be included in release plans.

Tip: As described in the Eclipse Foundation Development Process, milestones and release candidates are “almost releases”, not releases. You’ve likely noticed that we to some lengths to avoid using the word release and instead tend to speak of milestone builds. While the EMO may wince a little when you refer to content as, for example, an alpha release, please feel free to do so if that makes sense to you and your community.

There are no governance requirements to produce and distribute a milestone build. Specifically, the project team does not need to engage in any reviews (for example, release or progress reviews) prior to distributing a milestone build. Milestone builds may include intellectual property that has not been fully vetted; the project team does not need to wait for specific approvals from the Eclipse Foundation’s IP Team to disseminate milestone builds. The project team should, however, take care to ensure that — to the best of their knowledge and ability — the licenses of the content included in milestone builds is well-defined and compatible/consistent.

Milestone builds can be hosted wherever the project team hosts downloads. The project team must ensure that milestone builds are clearly described as pre-release software that is intended to engage and prepare consumers, test the build process, and to solicit feedback. Milestone builds can be referred to as alpha, beta, or whatever other terms make sense to the project team and community (the primary concern is that the community understand the nature of the content that they consume).

Tip: Be sure to specify the channels where milestone adopter should provide feedback.

If you have questions regarding the distribution of milestone builds, contact the EMO for assistance.